Capacity Planning

Plan and manage team capacity for effective sprint execution

Capacity Planning

Capacity planning helps teams understand how much work they can realistically commit to in a sprint. Elixion provides tools to track and plan capacity effectively.

Understanding Capacity

What is Capacity?

Capacity is the amount of work a team can complete during a sprint, measured in:

  • Hours - Actual time available
  • Story Points - Relative effort
  • Person-Days - Days of availability

Capacity vs. Velocity

| Concept | Definition | Use | |---------|------------|-----| | Capacity | Available time to work | Planning | | Velocity | Historical points completed | Forecasting |

Example:

  • Team capacity: 200 hours
  • Average velocity: 35 points
  • Use velocity to set sprint commitment

Setting Team Capacity

Access Capacity Planning

  1. Go to Sprints
  2. Select sprint
  3. Click Capacity tab

Individual Capacity

Set each team member's availability:

Sprint 15 Capacity
──────────────────────────────────────
Member      Days    Hours   Notes
──────────────────────────────────────
Alice       10      60      Full time
Bob          8      48      PTO Mon-Tue
Carol       10      60      Full time
Dave         5      30      50% allocated
Eve         10      60      Full time
──────────────────────────────────────
Total:      43     258

Adjustments

Account for:

Planned Absence:

  • Vacation/PTO
  • Holidays
  • Training
  • Conferences

Partial Allocation:

  • Multiple projects
  • Support rotation
  • On-call duties
  • Meetings

Other Factors:

  • New team members (reduced velocity)
  • Learning curve for new tech
  • Sprint ceremonies time

Capacity Calculator

Basic Calculation

Team Capacity = Σ (Member Days × Hours per Day)

Example:
- 5 members × 10 days × 6 hours = 300 hours
- Subtract planned absence: -24 hours
- Meeting overhead (15%): -41 hours
= Available Capacity: 235 hours

Hours per Day

Typical allocation:

8-hour workday
- 1 hour: Meetings (standup, ad-hoc)
- 0.5 hour: Email/communication
- 0.5 hour: Code review
- 6 hours: Focused work

Sprint Overhead

Account for ceremonies:

2-week sprint:
- Planning: 2 hours
- Standups: 10 × 0.25 = 2.5 hours
- Review: 1 hour
- Retro: 1.5 hours
= 7 hours per person

Capacity Views

Team Calendar

Visual availability calendar:

         Mon  Tue  Wed  Thu  Fri
Week 1:  ████ ████ ████ ████ ████
Alice    ▓▓▓▓ ▓▓▓▓ ▓▓▓▓ ▓▓▓▓ ▓▓▓▓
Bob      ░░░░ ░░░░ ▓▓▓▓ ▓▓▓▓ ▓▓▓▓  (PTO)
Carol    ▓▓▓▓ ▓▓▓▓ ▓▓▓▓ ▓▓▓▓ ▓▓▓▓
Dave     ▓▓░░ ▓▓░░ ▓▓░░ ▓▓░░ ▓▓░░  (50%)

▓ = Available  ░ = Unavailable

Capacity Chart

Compare commitment to capacity:

                    Capacity
                    ─────────
Sprint Points:      │████████░░│ 30/40
                    ─────────

By Member:
Alice      │██████░░░░│ 12/20
Bob        │████░░░░░░│  8/16
Carol      │████████░░│ 16/20

Workload Distribution

See how work is distributed:

Assignment Distribution
────────────────────────
Alice    ●●●●●●●○○○  70%
Bob      ●●●●●○○○○○  50%
Carol    ●●●●●●●●○○  80%
Dave     ●●●○○○○○○○  30%
Eve      ●●●●●●○○○○  60%
────────────────────────
Team Average: 58%

Planning to Capacity

Setting Commitment

Based on capacity and velocity:

Historical Velocity: 35 points
Team Capacity: Normal (no changes)
Recommended Commitment: 33-37 points

Adjustments this sprint:
- Bob out 2 days: -4 points
- New team member: -3 points
= Adjusted Recommendation: 28-32 points

Capacity vs. Commitment

Sprint 15 Overview
──────────────────
Capacity:     40 points (based on history)
Committed:    32 points
Buffer:       8 points (20%)
Status:       ✅ Healthy commitment

Warning Indicators

| Status | Meaning | Action | |--------|---------|--------| | ✅ Under capacity (< 85%) | Safe buffer | Consider adding work | | 🟡 At capacity (85-100%) | Risk of spillover | Monitor closely | | 🔴 Over capacity (> 100%) | Likely spillover | Reduce scope |

Advanced Planning

Skill-Based Capacity

Track capacity by skill:

Skill Capacity
──────────────
Frontend:    80 hours (Alice, Carol)
Backend:     100 hours (Bob, Dave, Eve)
DevOps:      40 hours (Dave, Eve)
Testing:     40 hours (All members)

Work Type Allocation

Plan by work type:

Sprint Allocation
─────────────────
New Features:  60%  (18 points)
Bug Fixes:     20%  (6 points)
Tech Debt:     15%  (5 points)
Support:       5%   (2 points)
─────────────────
Total:         100% (31 points)

Risk Buffer

Reserve capacity for unknowns:

Base Capacity:     40 points
Risk Buffer:       -6 points (15%)
Available:         34 points

Buffer Uses:
- Unexpected bugs
- Scope clarification
- Technical challenges

Tracking Utilization

Daily Tracking

Monitor actual vs. planned:

Day 5 of 10
─────────────
Planned Progress: 50%
Actual Progress:  45%
Status:          ⚠️ Slightly behind

Individual Utilization

Track per team member:

Member     Assigned  Completed  Utilization
──────────────────────────────────────────
Alice      12 pts    6 pts      50%
Bob         8 pts    5 pts      63%
Carol      16 pts    7 pts      44%
──────────────────────────────────────────

Capacity Reports

Generate reports:

  1. Go to Analytics > Capacity
  2. Select date range
  3. View:
    • Utilization trends
    • Capacity vs. completion
    • Team balance
    • Recommendations

Best Practices

Planning Accurately

Do:

  • Use historical data
  • Account for all absences
  • Include meeting overhead
  • Leave buffer (15-20%)

Don't:

  • Assume 100% capacity
  • Ignore vacation/holidays
  • Plan based on perfect conditions
  • Overcommit consistently

Maintaining Balance

Do:

  • Distribute work evenly
  • Match skills to tasks
  • Consider individual capacity
  • Monitor workload regularly

Don't:

  • Overload high performers
  • Ignore skill gaps
  • Wait until burnout
  • Compare individuals

Improving Over Time

Do:

  • Track actual vs. planned
  • Adjust calculations
  • Learn from patterns
  • Experiment with approaches

Don't:

  • Use same estimates forever
  • Ignore velocity trends
  • Blame capacity issues
  • Skip retrospective discussion

Integration with Planning

Sprint Planning Flow

1. Set capacity → Know available time
2. Review velocity → Understand past performance
3. Calculate commitment → Realistic target
4. Select items → Fill to target
5. Verify balance → Check distribution
6. Start sprint → Begin work

Continuous Improvement

Track capacity accuracy:

Sprint    Planned  Actual  Accuracy
─────────────────────────────────
Sprint 12   35      32      91%
Sprint 13   32      30      94%
Sprint 14   30      31      103%
Sprint 15   31      ?
─────────────────────────────────
Average:              96%

Next: Kanban Board - Visual task management